Outer Ring Road
|
Phase - I to be completed by mid 2008
Phase - II work to begin by December, 2007 |
Suburban area s; Creates new infrastructure and development activity around city
|
|
International Airport
|
Work in progress. Scheduled to be completed by summer of 2008
|
Shamshabad; initiates new infrastructure and development projects & residential zones at Bangalore road
|
|
Fab City
|
Infrastructure by APIIC in development;
Industrial activity to begin by late 2008
|
Srisailam Road; Much hype is already created where real infrastructure & development holds the key
|
|
Hardware Park
|
Land procurement & infrastructure development Work in progress
|
Srisailam Road - Sagar Road; limited impact because of low activity & land acquisition problems
|
|
Textile City |
work yet to be commenced
|
Cheguru Bangalore Road; limited impact around Timmapur - Kottur Zone
|
|
APIIC Commercial Zone
|
Infrastructure development from early 2008
|
Gandipet Road; Creates greater impact on land rates in surrounding areas & New residential zones
|
|
Internet City
|
Location & work schedule yet to be finalised
|
Koheda, Vijayawada Road; limited impact
|
|
Raheja IT Park & Infosys SEZ
|
Work in progress; to be completed by 2009
|
Annojiguda - pocaram belt - Warangal Road; Creates new commercial & residential development activity at Warangal Road |
|
Bio - Tech Park
|
II & III Phase work in progress at Genome Valley. To be completed by 2009
|
Turkapally @ Rajeev Rahadari; Creates new infrastructure and development activity around Shameerpet - Turkapally zone
|
|
Textile Park & IIC Commercial Zone
|
Development work in progress; to be completed by 2009
|
Gundla Pochampally, Medchal Road; New commercial & residentia projects will be developed at Medchal Road
|
|
Tellapur Township
|
Infrastructure in development; Work to commence by early 2008
|
Tellapur, Old / New Mumbai Road; new high-end residential more projects will be developed around the HUDA / TSI Township zone
|
|
APIIC Commercial Zone |
To be finalised
|
Rayadurgam & Manikonda, Old Mumbai Road
|
|
Rajeev Swagruha Mega Township
|
Work to commence by early 2008
|
Near Pocharam, Warangal Road. Limited impact
|
|
MLR Industry & Toopran Commercial Zone
|
Infrastructure development in progress
|
Near Toopran, Medchal Road. Limited impact
|